Platform Hardening
Four upgrades from the competitive assessment — with honest scores and what still needs a specialist system.
Scheduling (Primavera side)
5.5 → 7 / 10
+27%
Field work offline
6 → 7.5 / 10
+25%
Finance & KSA compliance
4 → 5.5 / 10
+38%
Links to other systems
5 → 6.5 / 10
+30%
Load test — background CPM
Schedules with 500+ activities are calculated in the background so the screen stays responsive. Try a mega-project size.
| Activities | Time | Where | Critical | Finish (day) |
|---|
XER fidelity check
Imports activities, logic, WBS, calendars (hours/day), resources & assignments, constraints, actual dates and cost. Activity UDFs and activity codes are shown and UDFs can be edited; other tables (notebooks, expenses…) are kept and written back on export with their task links re-pointed.
Still out of scope
- Calendars are applied as hours-per-day; holiday exceptions and multi-shift work patterns are read and kept but not used in the date maths.
- Leveling is a heuristic (float-ordered delays), not P6's priority-based leveler.
- Forensic delay analysis (windows, TIA for claims) stays in Primavera.